NPG Contracting was contracted by Sunshine Coast Council to upgrade Winston Road South at Palmwoods from the existing gravel road to a 4-metre-wide bitumen seal road with localised widening to 6m along an 850m section. The scope of works included:
The project was delivered without a safety incident or community complaint throughout the duration of works. All works were delivered on time and on budget.
Client
Sunshine Coast Council
Duration
January 2020 – March 2020
Services Supplied
NPG Contracting was contracted by Sunshine Coast Council to upgrade Winston Road South at Palmwoods from the existing gravel road to a 4-metre-wide bitumen seal road with localised widening to 6m along an 850m section.
NPG Contracting was the Principal Contractor engaged to deliver the land development of Huonbrook Estate in Terranora, Stage 17A civil construction including:
The supply of all labour, equipment and vehicles to prepare, deliver and document the installation of permanent scope for the rock pitching, gabion mattress and concrete safety barriers provide on the Eton Range Realignment Project.